On ScheduleSite Progress VerifiedLast activity 113d ago · Site Inactive

Highpoint 336 Residence

Highpoint Residences Ltd · Kilimani Road, Nairobi · Modern elegance with floor-to-ceiling Kilimani skyline views.

Construction Health
On Schedule
Last Site Activity
113 days ago
Last Milestone
Foundation Complete
Update Frequency
Every 14 days
Estimated completion:June 2028

Milestone Progress

40%
  1. Legal and Title ClearanceDone Jan 2023
  2. Foundation CompleteDone Nov 2023
  3. Superstructure CompleteIn Progress
  4. Building Envelope and RoofingEst. Aug 2027
  5. Practical CompletionEst. Jun 2028

GPS-Verified Photos

Verified Progress Timeline

Every record is GPS-locked, timestamped, and admin-reviewed before appearing here.

  • Structural Works📍 Location & Timestamp Verified✓ Record Approved10 Jun 2026
    Superstructure Progress — Levels 13 to 19 Complete

    Superstructure works continue steadily, incorporating the enhanced design specifications. Levels 13 through 19 are fully cast and cured. The team is currently working on level 20. MEP rough-in works, including electrical conduits and plumbing sleeves, are progressing on levels 1 through 8. Internal block work is complete on levels 1 through 6. The project is tracking toward Milestone 3 completion in December 2026.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload35%
  • Structural Works📍 Location & Timestamp Verified✓ Record Approved14 Mar 2025
    Design Enhancement Works — Wider Lift Lobbies and Staircase Upgrades Incorporated

    Following a design review, structural enhancements have been incorporated into the ongoing superstructure works. These include wider lift lobbies, improved staircase widths, and enhanced accessibility features on all floors. These upgrades have been fully integrated into the structural programme. The revised design is now reflected in all floors from level 13 upward. The project timeline has been reviewed, and the Q2 2028 completion date remains the target.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload31%
  • Structural Works📍 Location & Timestamp Verified✓ Record Approved30 Oct 2024
    Superstructure Progress — Levels 6 to 12 Complete

    The superstructure has reached level 12. All columns, suspended slabs, and staircase cores from levels 6 through 12 are complete and cured. Formwork striking is underway on level 11. Block work for internal partition walls is commencing on levels 1 through 4 concurrently with ongoing structural works on the upper floors.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload27%
  • Structural Works📍 Location & Timestamp Verified✓ Record Approved18 May 2024
    Superstructure Progress — Ground Floor to Level 5 Complete

    Superstructure works have commenced and are progressing well. Columns, beams, and suspended slabs from the ground floor through to level 5 have been cast and cured. The structural frame is taking shape and is visible from Kilimani Road. No structural issues have been recorded. Works are proceeding in line with the programme.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload20%
  • Milestone Completed📍 Location & Timestamp Verified✓ Record Approved22 Nov 2023
    Foundation Works Complete — Milestone 2 of 5

    Foundation works for Highpoint 336 are complete. Piling, pile caps, ground beams, and the slab on grade have been successfully cast and independently verified. The structural engineer's sign-off has been received. The project now advances to superstructure works. This marks the completion of Milestone 2 of 5.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload14%
  • Legal and Administrative📍 Location & Timestamp Verified✓ Record Approved10 Jan 2023
    Site Acquisition and Title Clearance Confirmed — Milestone 1 of 5

    Legal and title clearance for the Highpoint 336 site on Kilimani Road has been completed. All statutory approvals, including the NCA project registration and county building permit, are in place. Site hoarding and security have been established. This confirms the completion of Milestone 1 of 5 and marks the formal commencement of the project.

    📸 2 photos📍 -1.29832, 36.78093
    Progress at upload5%